Lighting and home electrics, written down

First fix cable planning: the decisions you cannot redo later

7 July 2026 · Planning

Electrical conduits in a plastered wall during renovation
Two weeks of thinking, buried for a decade.

First fix is the stage where conduit and cable enter the walls before plaster. A conduit drop added during first fix costs about 40 AED in materials; the same drop added after plaster costs a day of labour, filler and a full wall repaint, which runs 400 to 700 AED per wall in Dubai.

Which questions decide switch positions before the electrician starts?

Switch positions follow how the room gets used at 07:00, at 15:00 and at 22:00, not the symmetry of the plan drawing. A bedroom needs a switch at the door plus one at each side of the bed at 700 mm, and a living room needs the ceiling circuit killable from the sofa.

Stand at the door of each room and describe the three times of day out loud while an assistant marks the wall in pencil. A two way switch pair costs about 90 AED in modules and 6 metres of 1.5 mm2 cable at first fix. The same pair retro fitted through a plastered blockwork wall takes four hours plus making good.

What heights above finished floor do switches, sockets and wall lights sit at?

Standard domestic heights measure from finished floor level, which means after tile or timber, not after screed. Switches land at 1050 mm, general sockets at 300 mm, worktop sockets at 1150 mm, bedside sockets at 700 mm and wall lights at 1500 to 1600 mm.

ItemHeight above finished floorBack box depthReason for the dimension
Switches1050 mm35 mmReachable with an armful of shopping
General sockets300 mm47 mmAbove a 100 mm skirting, below the furniture line
Worktop sockets1150 mm47 mm150 mm above a 1000 mm counter, clear of a 500 mm splashback
Bedside sockets700 mm47 mmAbove a 550 mm side table top
Wall lights1500 to 1600 mm35 mmAbove the 1200 mm eye level of a seated adult
Floor socket boxFlush with floor75 mm below finished floorNeeds screed of at least 75 mm to bury the box

How many lighting circuits does a living room need at first fix?

A living room needs three switched lighting circuits: downlights, accent or cove, and a switched socket loop for floor and table lamps. Each lighting circuit runs on 1.5 mm2 cable protected by a 6 A breaker, and each socket circuit on 2.5 mm2 protected at 20 A behind a 30 mA RCD.

The extra cost of the third lighting circuit at first fix is one 1.5 mm2 cable run, one 20 mm conduit and one switch module, around 120 AED in total. Splitting the same circuit after plaster means chasing the wall, rewiring back to the board and repainting, which lands near 1200 AED, about ten times the first fix figure.

Pull one spare 1.5 mm2 cable to the ceiling centre and one to a feature wall in every main room, cap both ends, and photograph the caps. A dormant capped cable costs about 40 AED. The wall needed to add one later costs a day and a repaint.

Which cables are worth pulling even when no fitting is planned?

Four spare runs pay for themselves in most Dubai apartments: a control pair for future scene dimming, a ceiling centre drop, a cable to one feature wall, and a data run to the television wall. The four spares add about 200 AED at first fix against thousands after plaster.

Spare runCableDestinationCost at first fixCost after plaster
Scene control pair2 core 1.5 mm2Switch position to lighting boardabout 40 AED400 to 700 AED per wall
Ceiling centre drop1.5 mm2 twin and earthRoom centreabout 40 AEDCeiling opened, 600 AED and up
Feature wall lighting1.5 mm2 twin and earthOne wall per main roomabout 40 AED400 to 700 AED per wall
Television wall dataCat 6, 23 AWGMedia wall to router positionabout 80 AEDSurface trunking or 500 AED chase

How should conduit runs be photographed before plastering?

Photograph every wall with a tape measure held against a fixed reference such as a door frame, so that each conduit run has a dimension in the frame. Store the photographs in one folder per room, named by room, and keep a copy off the phone. Plaster hides the conduit for a decade.

A conduit buried at 25 mm below plaster survives a picture hook and does not survive a 6 mm masonry bit driven to 60 mm. The photograph set is the only record that tells a drill operator where the vertical drop from a switch box runs, and a photograph set takes 20 minutes to shoot for a three bedroom apartment.

Which questions should a client answer before the electrician starts?

Six answers turn a wiring drawing from a guess into an hour of work: grouped lights, equipment positions, floor sockets, scene control routes, always live sockets and outdoor supply. Every answer below carries a cable decision that becomes permanent once the plasterer finishes the room.

  • Which lights should come on together, and from which door?
  • Where will the television, the router and the printer actually stand, and how many sockets does each position need?
  • Does any room need a floor socket, and does the screed reach 75 mm depth for the box?
  • Is a scene controller wanted later, and is there a 2 core route back to the lighting board?
  • Which sockets stay live when the apartment main switch is off, such as the fridge and the router?
  • Does the balcony need a 16 A outdoor rated supply for a heater, a pump or a light?

Once the six answers are written down, the wiring drawing takes about an hour and the second fix stops producing surprises. Related: dimming without flicker.

Zero Ohm, 2026. Written by hand in Dubai. About | Sitemap